Industry explainer · U.S. view · Electricity · Data centers · Bottlenecks

Power Grid Equipment Industry Explained: The U.S. View

After years of little growth in electricity demand, the U.S. grid is being asked to grow again, mainly because of data centers, and the slowest parts to expand are the physical equipment and connections. Every new power plant or large load needs transformers, switchgear, transmission lines and substations. Those are in short supply: PwC analysts cited by pv magazine say lead times for high-capacity transformers can reach four years, and prices for these components have risen about 80% over five years. Wood Mackenzie estimates U.S. demand for generator step-up transformers rose 274% from 2019 to 2025. The strain shows up in prices. In PJM, the grid operator serving 67 million people across 13 states and Washington, D.C., the auction for capacity in the 2027/28 delivery year cleared at the $333.44 per megawatt-day price cap and still fell 6,623 megawatts short of the reliability target. PJM said nearly 5,100 MW of the 5,250 MW increase in forecast peak load came from data centers. The EIA expects PJM wholesale power prices to rise 41% in 2026.

PJM auction
2027/28 capacity cleared at the $333.44/MW-day cap, 6,623 MW short
Data centers
PJM: about 5,100 MW of a 5,250 MW peak load increase is data centers
Transformers
Lead times for high-capacity transformers can reach four years (PwC)
IN ONE LINEThe grid is the bottleneck; transformers and capacity are scarce.

How the chain works

U.S. power grid chain: new demand from data centers, factories and electrification needs generation and grid connections; power plants connect through step-up transformers and high-voltage transmission lines to substations and distribution networks; transformers, switchgear and cables are the bottleneck, with long lead times and heavy reliance on imports; grid operators such as PJM run capacity markets that set prices for having enough supply New load data centers Grid operators PJM, ERCOT Generation · capacity Power plants gas, nuclear, solar Transformers · bottleneck Transformers lead times to 4 yrs Lines and substations Transmission lines, switchgear Utilities, users higher bills PJM 2027/28 capacity price at the $333/MW-day cap
New load, mainly from data centers, needs generation and grid connections. Power plants connect through transformers and transmission lines to substations and distribution. Transformers and switchgear are the bottleneck; grid operators such as PJM use capacity markets to pay for enough supply.Swipe sideways on a phone to see the full chart.

Generation, transformers and transmission

GenerationTransformers and switchgearTransmission and substations
2026 signalPJM capacity price at the cap two auctions in a rowLead times up to four years; prices up about 80% in five yearsSubstation transformer demand up 116% from 2019 to 2025 (Wood Mackenzie)
What limits supplyTurbines, permits, interconnectionFactory capacity, electrical steel, copperPermits, rights of way
Who paysCapacity and energy pricesUtilities and developersUtility customers through rates
What to watchCapacity auctionsNew U.S. factoriesTransmission approvals

Demand returns to the grid

For years U.S. utilities planned for little or no demand growth. Data centers changed that. In PJM's December 2025 release on its 2027/28 capacity auction, the forecast peak load was about 5,250 MW higher than for the previous auction, and nearly 5,100 MW of that increase was attributed to data center demand.

PJM's executive Stu Bresler said the auction "leaves no doubt that data centers' demand for electricity continues to far outstrip new supply." The auction secured 134,479 MW from generation and demand response, plus 11,299 MW through utilities' own plans, but the total was 6,623 MW short of the requirement for a 20% reserve margin, leaving 14.8%.

Transformers: the equipment bottleneck

Transformers step voltage up and down between power plants, transmission lines and users. According to pv magazine, citing Reuters Events and PwC, lead times for high-capacity transformers extend to as long as four years and prices have risen roughly 80% over five years. Wood Mackenzie data show demand for generator step-up transformers up 274% and substation transformers up 116% from 2019 to 2025.

Supply is tight because transformers need grain-oriented electrical steel and copper, and U.S. makers depend heavily on imports for that steel. Manufacturers are investing: Hitachi Energy has committed more than $1 billion, including a plant in South Boston, Virginia due in 2028, and Siemens $421 million for a transformer factory in Charlotte, North Carolina.

Prices for customers

Capacity markets pay power plants to be available at peak times. PJM's 2027/28 auction cleared at $333.44 per megawatt-day, the price cap, up 1.3% from the previous auction, which was also at the cap. Cleared supply times the price totals about $16.4 billion, though not all load pays that price.

Energy prices are rising too. The EIA's October 2026 outlook expects U.S. wholesale electricity prices to average $52 per megawatt-hour in 2026, 11% above 2025, and PJM prices to rise 41%. Higher wholesale costs feed into retail bills over time.

How the U.S. view differs from the China view

The Chinese version of this page looks at the world's largest grid builder: China's state grid companies run huge, planned investment programs, and Chinese makers of transformers and ultra-high-voltage equipment are expanding exports.

The U.S. problem is the opposite: a fragmented system of utilities, grid operators and regulators, slow permitting, and limited domestic factory capacity for transformers. The shortage is less about money than about how fast equipment and connections can be built.

2025: PJM's capacity auction hits the cap again

In December 2025 PJM ran its auction for the 2027/28 delivery year. Demand forecasts had risen again, almost entirely because of data centers.

The price cleared at the $333.44 per megawatt-day cap for the second auction in a row, and supply still fell 6,623 MW short of the reliability requirement.

New supply could not come fast enough: power plants need turbines and transformers with multi-year lead times. Prices, not new capacity, absorbed the demand shock first.

What this shows
  • Data centers are the main source of new U.S. power demand.
  • Grid equipment lead times limit how fast supply can respond.
  • Capacity prices rise first; customers pay later through bills.

Common misreadings

MythThe grid can connect any new data center quickly.

RealityPJM's 2027/28 auction fell 6,623 MW short of its reliability target.

MythTransformers are a commodity product.

RealityLead times for high-capacity units can reach four years, per PwC.

MythPower prices only move with natural gas.

RealityEIA expects PJM wholesale prices up 41% in 2026, far more than the national 11%.

MythHigher prices instantly bring new supply.

RealityPJM's capacity price hit the cap twice in a row while shortfalls persisted.

Demand, equipment and policy: scenarios

ScenarioMain effectHow it passes through
Data center load keeps growingGrid operatorsHigher capacity prices, more shortfalls
New transformer factories openEquipment supplyShorter lead times
Price cap expiresCapacity pricesPrices could rise above today's cap
Data centers bring own powerGrid demandLess strain on shared grid
Copper and steel tariffs riseEquipment costsHigher transformer and cable prices
Transmission permitting reformNew linesFaster connections, lower congestion

Supply and demand by segment

SegmentSupply rigidityConcentrationNew demandPolicy roleWhat to watch
GenerationHigh (turbines, permits)MediumYes (data centers)Very high (state, federal)Capacity auctions
Large power transformersVery high (years)High (imports)YesHigh (tariffs)Lead times
Transmission linesVery high (permits)MediumYesVery highApprovals
Distribution equipmentMediumMediumYesHigh (utility rates)Utility capex

Supply rigidity: how long new capacity takes and whether money can speed it up. Concentration: whether output sits in a few countries or companies. The more rigid and concentrated, the more prone to shortages.

How to track it

IndicatorWhat it tells youWhere to find it
PJM capacity auction resultsTightness of supplyPJM news releases, free
Wholesale electricity price forecastsCost pressureEIA Short-Term Energy Outlook, monthly, free
Transformer lead times and pricesEquipment bottleneckIndustry reports and news coverage
Utility capital spending plansGrid investmentUtility quarterly results, free
Gas turbinesNew generationU.S. view: gas turbines

Sources

Last updated 2026-10-18.