Industry explainer · U.S. view · Data centers · AI · Infrastructure

Data Center Cooling and Power Industry Explained: The U.S. View

AI accelerators turn almost all the electricity they use into heat, and racks of them now draw far more power than the servers data centers were designed for. That has created a boom for the equipment around the chips: switchgear and transformers that bring power in, uninterruptible power supplies (UPS) and busways that distribute it, and cooling systems that take the heat out. Air cooling is reaching its limits, so the newest AI racks use liquid cooling, piping coolant directly to cold plates on the chips; even network switches now come in liquid-cooled versions. Vertiv, a leading U.S. supplier of data center power and cooling, reported second-quarter 2026 sales of $3.27 billion, up 24%, with Americas sales up 29%, and raised its 2026 forecast to $13.8–14.2 billion, or 30–32% organic growth, guiding 34–36% organic growth for the third quarter. GE Vernova said its data center orders for grid equipment passed $5 billion in the first half of 2026, more than double all of 2025. The limits are factory capacity, supply-chain congestion and, above all, how much grid power is available.

Vertiv
Q2 2026 sales $3.27B, up 24%; 2026 organic growth forecast 30–32%
Grid gear
GE Vernova data center orders over $5B in H1 2026, double all of 2025
Liquid
Arista introduced liquid-cooled 1.6T AI switch platforms in 2026
IN ONE LINEAI racks are too hot for air; liquid cooling and power gear boom.

How the chain works

Data center power and cooling chain from a U.S. view: electricity arrives from the grid or on-site generation through transformers and switchgear; uninterruptible power supplies and power distribution feed the racks; AI racks draw so much power that air cooling is no longer enough, so liquid cooling loops carry heat away to chillers and heat rejection equipment Grid power or on-site plant Switchgear transformers Power · UPS, distribution UPS, busways power to racks Cooling · liquid Liquid cooling direct to chip Heat rejection Chillers heat out AI racks GPUs, servers Vertiv expects 30–32% organic growth in 2026
Power arrives from the grid or on-site plants through switchgear and transformers, then UPS systems and busways feed the racks. AI racks are too dense for air alone, so liquid cooling (dashed line) carries heat to chillers and heat-rejection equipment.Swipe sideways on a phone to see the full chart.

Power equipment, liquid cooling and heat rejection

Power distributionLiquid coolingHeat rejection
JobBring power in and keep it uninterruptedRemove heat at the chipMove heat out of the building
EquipmentSwitchgear, transformers, UPS, buswaysCold plates, coolant distribution units, pipesChillers, dry coolers
2026 signalGE Vernova data center orders over $5B in H1Liquid-cooled switches launched by AristaVertiv raised 2026 guidance
What to watchLead times, grid connectionsShare of new racks liquid-cooledWater and power use

Why AI changes the building

A data center is mostly a machine for delivering power and removing heat. AI accelerators pack much more power into each rack, so the same building needs heavier power distribution and much stronger cooling. Moving air through a hot rack becomes inefficient, and liquid, which carries far more heat, takes over at the chip.

The change reaches beyond servers. Arista's second-quarter 2026 release introduced 1.6 Tbps AI networking platforms including liquid-cooled options, and switch makers are cutting power use with new optics. Every watt saved on networking or cooling is a watt available for accelerators.

The suppliers' numbers

Vertiv reported second-quarter 2026 net sales of $3,274 million, up 24% from a year earlier, including 18% organic growth; Americas sales rose 29.2%. Its adjusted operating margin was 22.6%, up 4.1 percentage points. Chief executive Giordano Albertazzi said demand for AI and general compute continues to intensify. Vertiv raised its 2026 sales forecast to $13.8–14.2 billion and guided third-quarter organic growth of 34–36%.

Upstream, grid equipment makers are seeing the same demand. GE Vernova said its Electrification segment's data center orders exceeded $5 billion in the first half of 2026, more than double the 2025 total, and that segment's equipment backlog reached $40.6 billion.

Limits: factories, supply chains and power

Growth is constrained by how fast equipment can be built and delivered. Vertiv said second-quarter revenue reflected minor timing shifts, mainly from temporary supply chain congestion and multi-phase project schedules, which it expected to resolve in the second half.

The bigger limit is power itself. PJM said data centers accounted for nearly 5,100 MW of the 5,250 MW increase in its forecast peak load for 2027/28, and its capacity auction fell short of the reliability target. On-site generation is one response, which adds to demand for gas turbines.

How the U.S. view differs from the China view

The Chinese version of this page looks at Chinese makers of liquid cooling parts, power supplies and server components, many of which supply global server and data center builders, and at China's own computing centers.

From the U.S. side, the largest AI data center build-out is at home, and the binding constraint is less the cooling hardware than the power: grid connections, transformers and generation. Equipment makers with U.S. factories and service networks benefit most.

2026: the infrastructure behind AI

As hyperscalers raised capital spending in 2026, orders for data center power and cooling equipment rose with it.

Vertiv raised its full-year outlook to 30–32% organic growth, and GE Vernova's data center orders for grid equipment more than doubled.

Even with strong demand, deliveries were limited by supply chain congestion and by how much grid power new sites could get.

What this shows
  • AI data centers need new power and cooling designs, not just more servers.
  • Liquid cooling is becoming standard for the densest AI racks.
  • Grid power is the ultimate limit on how fast data centers can grow.

Common misreadings

MythData center spending is mostly chips.

RealityPower and cooling suppliers like Vertiv expect 30–32% organic growth in 2026.

MythAir cooling can handle AI racks.

RealityEven switches now come in liquid-cooled versions for AI clusters.

MythEquipment shortages are the main limit.

RealityGrid capacity is tighter: PJM's 2027/28 auction fell short of its reliability target.

MythOnly the data center owner benefits.

RealityGrid equipment makers also gain: GE Vernova's data center orders more than doubled.

Rack density, power and spending: scenarios

ScenarioMain effectHow it passes through
Racks get denserCooling demandMore liquid cooling per rack
Grid connections delayedNew sitesMore on-site power, slower openings
Hyperscaler capex risesEquipment ordersHigher backlogs
Supply chain congestion easesDeliveriesRevenue catches up with orders
Water restrictions tightenCooling designShift to closed-loop systems
AI spending slowsNew projectsOrder growth slows

Supply and demand by segment

SegmentSupply rigidityConcentrationNew demandPolicy roleWhat to watch
Switchgear and transformersVery high (lead times)HighYesMediumLead times
UPS and power distributionMediumHighYesLowSupplier guidance
Liquid coolingMedium (new lines)MediumYes (AI racks)LowAdoption rate
Heat rejectionMediumMediumYesMedium (water rules)Project pipelines

Supply rigidity: how long new capacity takes and whether money can speed it up. Concentration: whether output sits in a few countries or companies. The more rigid and concentrated, the more prone to shortages.

How to track it

IndicatorWhat it tells youWhere to find it
Power and cooling suppliers' guidanceEquipment demandVertiv quarterly results, free
Data center orders at grid equipment makersUpstream demandGE Vernova quarterly results, free
Grid capacity and data center loadPower constraintPJM releases, EIA outlook, free
Hyperscaler capexBudget for new sitesU.S. view: AI compute
Power gridThe biggest constraintU.S. view: power grid

Sources

Last updated 2026-10-18.

This page explains the structure and supply-demand logic of an industry for educational purposes. It does not refer to any specific security and is not investment advice. Figures are dated and sourced; they may have changed since, so check the latest official data.